Skeena says Eskay Creek is targeting initial production in the second quarter of 2027 as construction continues
Thunder Bay – Mining Desk – Skeena Gold & Silver says it is aiming for initial production at its Eskay Creek gold and silver project in northwestern British Columbia in the second quarter of 2027.
The company repeated the target Monday as it released third-quarter financial results and announced an operations leadership appointment. Eskay Creek, in B.C.’s Golden Triangle, is under construction.
Skeena’s November corporate presentation said overall project progress was more than 80 per cent complete as of Oct. 31. It also said ore stockpiling began in October.
Those figures and the production target are company-reported. Initial production is not the same as commercial production, when a mine is operating at a sustained level. Skeena’s filing says management expects commercial production in 2027, while warning that construction, commissioning, financing and other risks could affect the schedule.
The company also named Sébastien Fortin senior vice-president of operations as it prepares for the transition from construction to production.
Source notes: Skeena’s Nov. 16 financial-results release filed with the U.S. Securities and Exchange Commission; Skeena November corporate presentation, reporting progress as of Oct. 31