Gold producers including Agnico Eagle, Alamos and Barrick say they expect to meet their 2026 production targets
THUNDER BAY ON – Mining News Service – This announcement comes even as a major expansion at Alamos’s Island Gold District in Northern Ontario faces a delay.
In third-quarter results released between late October and early November, the companies reported strong cash generation amid high gold prices. But the reports also pointed to cost pressures, changes to mine plans and construction work that will take longer than expected.
Alamos said commissioning of its Phase 3+ shaft at the Island Gold District is expected to finish in mid-2027, about one quarter later than previously planned. The company said more time is needed to complete the system for handling ore and waste.
The district produced a record 68,700 ounces of gold in the third quarter. Alamos said the operation remains on track to meet its annual production target of 290,000 to 310,000 ounces.
Across the company, Alamos produced 119,000 ounces in the quarter and said it expected to meet its full-year target, which it revised in July. It also said short-term delays at Island Gold and its Puerto Del Aire project in Mexico, along with previously disclosed constraints at Ontario’s Young-Davidson mine, were expected to affect near-term production and costs into 2027.
Agnico Eagle expects lower end of range
Agnico Eagle reported payable gold production of 814,012 ounces in the third quarter and said it remained on track to meet its annual production and cost guidance.
The company expects full-year production near the lower end of its 3.3-million-to-3.5-million-ounce range. It attributed that outlook to an adjusted mine plan at the Barnat open pit at Canadian Malartic in Quebec, following a rock mass movement reported in July.
Agnico Eagle also expects costs near the upper end of its guidance range. In Northern Ontario, it said project infrastructure continued to advance at Upper Beaver and Detour Lake.
Barrick reported production of 816,000 ounces of gold in the quarter and maintained its annual target of 2.9 million to 3.25 million ounces. Centerra Gold reported 75,429 ounces and said it remained on track to meet production guidance at its Mount Milligan mine in British Columbia and its Öksüt mine in Türkiye.
AngloGold Ashanti also reaffirmed its annual guidance, although its quarterly gold production fell nine per cent from a year earlier and its costs rose.
The results came during a quarter in which gold averaged US$4,262 an ounce, according to the World Gold Council, an industry group. It estimated that central banks and other official institutions added a net 321 tonnes to reserves, up 42 per cent from a year earlier. Total gold demand, however, was one per cent lower than a year earlier.
The companies’ guidance represents their expectations, not guaranteed year-end results.
For Northern Ontario, the timing of Island Gold’s shaft commissioning and progress at Agnico Eagle’s projects will be important developments to watch.