Gold Corp Reports 97,000 Ounces at Red Lake Mine

1043
Of concern to many First Nation leaders going forward in an evolving 21st Century mining era, are issues around the environment, social impacts and economic benefits.
Of concern to many First Nation leaders going forward in an evolving 21st Century mining era, are issues around the environment, social impacts and economic benefits.

gold bars

Gold Corp Reports Quarterly Revenues

TORONTO – Mining – Gold Corp is reporting that at the company’s operation in Red Lake in Ontario, gold production for the third quarter was 97,000 ounces at an all-in sustaining cost of $986per ounce and $640 per ounce on a by-product basis.

As expected, gold production during the quarter was lower than the second quarter of 2013 due to mining lower grade blocks in the 41 and 45 levels and the planned commencement of the 47- 46 level de-stress work. Red Lake remains on track to meet gold production guidance for the year of between 475,000 and 510,000 ounces.

GOLDCORP INC. has reported adjusted quarterly revenues of $1.2 billion, generating adjusted net earnings of $190 million, or $0.23 per share, compared to $441 million, or $0.54 per share, in the third quarter of 2012.  Revenues were $929 million and net earnings were $5 millionin the quarter compared to net earnings of $498 million in the third quarter of 2012.  Adjusted operating cash flow1,3was $375 million, or $0.46 per share, compared to $686 million, or $0.85 per share, in the third quarter of 2012.

Third Quarter 2013 Highlights

  • Adjusted revenues totaled $1.2 billion.
  • Gold sales totaled 652,100 ounces1 on gold production of 637,100 ounces.
  • All-in sustaining costs totaled $9921,4 per ounce; cash costs totaled $551 per ounce on a by-product basis1,5 and $706per ounce on a co-product basis1,5.
  • Adjusted operating cash flow totaled $375 million, or $0.46 per share.
  • Adjusted net earnings were $190 million, or $0.23 per share.
  • Dividends paid amounted to $122 million.
  • Revised initial cost and schedule at Cerro Negro project in Argentina to affect 2014 outlook.
  • Amendments to the Special Lease Agreement (“SLA”) for the Pueblo Viejo mine were ratified by the President of theDominican Republic.
  • Signed the Obishikokaang Collaboration Agreement on behalf of the Red Lake Mine with the Lac Seul First Nation.

“Operations throughout our portfolio performed as planned during the third quarter and we remain on track to achieve our annual production and cost guidance,” said Chuck Jeannes, Goldcorp President and Chief Executive Officer. “Most importantly, our focus on operational discipline and cost containment delivered positive results. Most of our mines saw meaningful reductions in costs compared to the previous quarter, with particularly impressive improvement at some of our higher-cost operations such as Porcupine in Ontario.  The operating teams at each mine have continued to implement innovative ways of adding value consistent with our Operating for Excellence program, and as additional initiatives take hold we look forward to a positive impact on our financial results.  Two of our three current development projects are set to begin contributing to our low-cost production profile in 2014, and given our strong balance sheet and low debt levels, we will enter this new growth phase an efficient, well-capitalized organization with our peak year of capital spending behind us.

“The pace of development at Éléonore and Cochenour is especially impressive, and the team at Cerro Negro inArgentina deserves special mention for the progress they made this quarter in a challenging environment.  However, factors in Argentina, including permitting delays, an unsustainable foreign exchange rate and uncertainty with respect to provincial taxation demands continue to present significant challenges to our project.  In response, we have suspended exploration and deferred certain development activities at Cerro Negro, and we are revising our guidance for first gold production and capital costs. We are in the midst of our planning and budgeting process for 2014 and, despite the delay at Cerro Negro, we continue to anticipate strong company-wide production growth in 2014 along with reduced all-in sustaining costs, which should drive higher margins and operating cash flow.”

Financial Review

Gold sales in the third quarter were 652,100 ounces on production of 637,100 ounces.  This compares to sales of 617,800 ounces on production of 592,500 ounces in the third quarter of 2012. Silver production totaled 7.7 million ounces compared to silver production of 8.5 million ounces in the prior year’s third quarter.  Costs were $992 per ounce of gold on an all-in sustaining basis, $551 per ounce on a by-product basis and $706 per ounce on a co-product basis.

Net earnings in the quarter totaled $5 million compared to net earnings of $498 million in the third quarter of 2012. Adjusted net earnings in the third quarter totaled $190 million, or $0.23 per share, compared to $441 million, or $0.54per share, in the third quarter of 2012.  Adjusted net earnings in the third quarter of 2013 primarily exclude the retroactive impacts of the Pueblo Viejo SLA amendments, losses from the foreign exchange translation of deferred income tax liabilities, and foreign exchange losses on capital projects, but include the impact of non-cash stock-based compensation expenses which amounted to approximately $24 million, or $0.03 per share, for the quarter.  Adjusted operating cash flow was $375 million compared to $686 million in last year’s third quarter.  The average realized gold price for the quarter was $1,339 per ounce compared to $1,685 per ounce during the year-ago quarter

Gold Corp Operations

Canada

At Red Lake in Ontario, gold production for the third quarter was 97,000 ounces at an all-in sustaining cost of $986per ounce and $640 per ounce on a by-product basis. As expected, gold production during the quarter was lower than the second quarter of 2013 due to mining lower grade blocks in the 41 and 45 levels and the planned commencement of the 47- 46 level de-stress work. Red Lake remains on track to meet gold production guidance for the year of between 475,000 and 510,000 ounces.

Drilling continued on the NXT zone during the quarter. To date, results indicate that the zone remains open vertically and to the west. Several drills are targeting this zone both from the 4199 exploration drift, the new 47 level exploration drift and from existing infrastructure at higher levels in the mine.

At Porcupine in Ontario, gold production in the third quarter increased to 76,000 ounces at an all-in sustaining cost of$921 per ounce and $637 per ounce on a by-product basis.  These are the lowest costs at Porcupine since the fourth quarter of 2011, driven by strong production and successful Operating for Excellence initiatives. The Hoyle Pond underground operation experienced similar grades on 7% lower tonnage due to the optimization of long-hole sequencing to remove marginal tonnes. The Dome underground operation experienced 61% higher grades and 18% lower tonnage due to optimization of the mining sequence. Material reclaimed from stockpile provided 22% higher tonnage due to higher mill throughput.

The Hollinger project continues to be delayed pending final permitting. The Environmental Compliance Approval is expected to be issued by the Ontario Ministry of the Environment in the fourth quarter of 2013.  On-site work focused on remediation of critical voids and reverse circulation drilling to define ore limits prior to mining. A revised mine plan has been developed to support an economic project at lower gold prices.

Mexico

Third quarter gold production at Peñasquito increased to 113,900 ounces compared to 88,100 ounces in the second quarter, driven by higher grade consistent with the mine plan.  Total cash costs decreased compared to the second quarter to $830 per ounce on an all-in sustaining cost basis and $403 per ounce on a by-product basis.  Silver production increased to 5.9 million ounces; lead production totaled 41.0 million pounds and zinc production totaled 76.3 million pounds.  Process plant throughput in the quarter averaged 109,947 tonnes per day with water availability as expected.  Gold production at Peñasquito is expected to meet narrowed guidance for the year of between 370,000 and 390,000 ounces.

The Northern Well Field project, designed to increase overall water availability at Peñasquito, continued on schedule and the final pipeline routing has been selected. Completion of land and access agreements continued to proceed throughout the quarter and engineering is essentially complete. Construction management bids were received and are under evaluation, with construction activities planned to commence in the fourth quarter of 2013.

Exploration at Peñasquito is focused on defining the intersection of the copper-gold sulphide-rich skarn mineralization and porphyry deposit located below and adjacent to current mineral reserves. The first phase of this exploration program is nearly complete, with 3,260 metres drilled in the third quarter, in four holes.

Gold production at Los Filos was 73,400 ounces in the third quarter at an all-in sustaining cost of $891 per ounce and$640 per ounce on a by-product basis.  Gold production was lower than expected as a result of severe storms that interrupted delivery of supplies to the mine site.  The 2013 exploration program was completed during the quarter and the modeling process is underway.  The crushing and agglomeration plant expansion is progressing and anticipated to be completed by the end of 2013.

Central America

At Pueblo Viejo, third quarter gold production totaled 75,400 ounces at an all-in sustaining cost of $661 per ounce and$553 per ounce on a by-product basis.  Production decreased compared to the second quarter primarily due to lower tonnage processed.  The decrease in tonnes milled during the quarter resulted from down time to complete Phase 2 modifications to the autoclaves and impacts from the rainy season that increased water-treatment and lime requirements.   Phase 2 modifications are complete on all four autoclaves and each has been successfully tested at design throughput of 300 tonnes per hour.  Silver recoveries continue to be negatively impacted by heating and lime issues, and remediation activities continued during the quarter.  Optimization of plant operations continues with a current focus on the limestone circuit.  Production in the first three quarters of 2013 was lower than expected as a result of these ongoing modifications to the autoclaves. It is anticipated that production is expected to be at the lower end of the guidance range of between 330,000 and 435,000 ounces (on a 40% basis).

The new 215 MW power plant was commissioned on schedule during the third quarter with commercial operations commencing early in the fourth quarter.

Growth Projects

Cerro Negro

Construction continued to advance in the third quarter of 2013 in key areas of the Cerro Negro project including plant construction, infrastructure, and mine development. However, the project has been subject to a number of challenges, including an approximate six-month delay in the start of construction for the main power transmission line resulting from the delay in issuance of necessary permits; significant in-country inflation at an annualized rate of approximately 25 to 30%, without a corresponding decline in the Peso exchange rate; labour and contractor productivity issues; and uncertainty related to the recently-enacted Resource Tax imposed by the Provincial Government of Santa Cruz.  As a result of these challenges, the Company has elected to defer certain capital spending at Cerro Negro, including the suspension of all exploration activity, and deferral of further development of the Mariana Norte deposit until late 2014.  These challenges have resulted in a revised schedule and initial capital cost estimate for Cerro Negro.  The Company now expects first gold production in mid-year 2014 with commercial production expected in the fourth quarter of 2014. The revised initial capital cost estimate is now expected to be between $1.6 and $1.8 billion, including anticipated continued inflation at current rates and an assumed exchange rate for the Peso of 6:1 US$ for 2014.  The Company now expects estimated gold production of between 130,000 and 180,000 ounces in 2014.  As a result of previous exploration success in the Eureka and Mariana Central veins and the delay of plant startup, the suspension of development of Mariana Norte is not expected to impact gold production levels during the first five years of operations.

Éléonore

Engineering activities progressed significantly during the third quarter of 2013 in all areas on-site. Overall surface construction progress reached 65%.  Despite challenges associated with wildfires and a province-wide construction strike this summer, the project remains on track for first gold by the end of 2014.

The exploration ramp has now reached 3,645 metres in length which corresponds to a vertical depth of approximately 560 metres below surface. The ramp is planned to connect with the main mine level (650m level) in November of this year, creating a secondary egress with a complete ventilation circuit. In parallel with the ramp development, four other development crews were active during the quarter excavating mining levels in the Upper Mine.  A significant milestone was reached with first ore development from the 410 metre level.  The production shaft has now reached a depth of 525 metres and is expected to reach approximately 700 metres by the end of the year, in line with plan.

Exploration activities during the third quarter focused on in-fill drilling in the Upper and Lower Mine areas and exploration in the Lower Mine area. A total of 17,128 metres of diamond drilling was completed from working platforms in the exploration ramp and at the 650 metre level, as compared to 23,528 metres in the prior quarter. Drilling progress was impacted during the current quarter by the forest fire evacuation in early July resulting in a delay in development. Currently, six diamond drills are active at the site.

Cochenour

At Cochenour in the Red Lake district, the haulage drift has now advanced to 80% completion.  The advance rate in the drift was reduced to address poor ground conditions related to a talc zone. Two drills continue to work in the haulage drift to test the potential of the underexplored area. The first drill platform for underground exploration diamond drilling of the Bruce Channel Deposit is being excavated and drilling has commenced in the fourth quarter. The Cochenour project remains on track for first gold in the first half of 2015.

Camino Rojo

At Camino Rojo near Peñasquito, exploration activities during the third quarter were focused on in-fill drilling and the extraction of core samples for metallurgical studies of the West Extension and Represa zones. Eleven core drills operated for a total 40,231 metres drilled in 63 holes. A total of 91.4 tonnes of core samples were shipped for metallurgical testing, including 42.3 tonnes from the West Extension, and 49.1 tonnes from the Represa zone.

El Morro

On October 22, 2013, the Environmental Assessment Commission of Atacama analyzed a final report prepared by the Chilean environmental permitting authority (SEA) and unanimously decided on the reinstatement of the environmental permit for the El Morro project, which had been suspended since April 27, 2012.  The permit was suspended pending the definition and implementation by the SEA of a community consultation process which corrects certain deficiencies in that process as specifically identified by the Antofogasta Court of Appeals.  The project continues with community engagement, optimization of project economics, and evaluation of alternatives for a long-term power supply.

Guidance Update

The Company today provided updated guidance for 2013 within a narrower range of between 2.6 and 2.7 million ounces at an all-in sustaining cost of between $1,050 and $1,100 per ounce; $550 and $575 per ounce on a by-product basis; and $700 to $725 per ounce on a co-product basis. Capital spending remains on track with guidance of$2.6 billion, a reduction from the original guidance of $2.8 billion for the year.

With respect to 2014, the Company is in the midst of its annual planning and budgeting process.  Previous 2014 gold production guidance of between 3.2 and 3.5 million ounces included approximately 400,000 ounces of gold from Cerro Negro.  The Company will provide actual 2013 gold production as well as 2014 production, cost and capital spending guidance in early January 2014.

Commitment to Partnerships

Demonstrating its commitment to partnerships Goldcorp and the Lac Seul First Nation signed the Obishikokaang Collaboration Agreement which sets a framework for continued consultation and support for current and future operations of Red Lake Gold Mines and defining the long-term benefits for the First Nation.  The agreement will bring recognition and economic benefits to Lac Seul First Nation, comprised of about 3,200 band members with significant historical ties to the development of the Red Lake gold camp.  Many band members reside within the municipality ofRed Lake.

Goldcorp is one of the world’s fastest growing senior gold producers. Its low-cost gold production is located in safe jurisdictions in the Americas and remains 100% unhedged.

This release should be read in conjunction with Goldcorp’s third quarter 2013 interim consolidated financial statements and MD&A report on the Company’s website, in the “Investor Resources – Reports & Filings” section under “Quarterly Reports”.

Conference Call and Webcast

A conference call will be held on October 24, 2013 at 10:00 a.m. (PDT) to discuss the third quarter results. Participants may join the call by dialing toll free 1-800-355-4959 or 1-416-695-6617 for calls from outside Canada and the US.  A recorded playback of the call can be accessed after the event until November 24, 2013 by dialing 1-800-408-3053 or 1-905-694-9451 for calls outside Canada and the US.  Pass code: 5331726.  A live and archived audio webcast will also be available at www.goldcorp.com.

Enhanced by Zemanta
Previous articleTELUS Acquires Public Mobile
Next articleRotary Works to End Polio
NetNewsledger.com or NNL offers news, information, opinions and positive ideas for Thunder Bay, Ontario, Northwestern Ontario and the world. NNL covers a large region of Ontario, but are also widely read around the country and the world. To reach us by email: newsroom@netnewsledger.com Reach the Newsroom: (807) 355-1862